662 Phil. 771

SECOND DIVISION

[ G.R. No. 182967, April 06, 2011 ]

PHILIPPINE NATIONAL RAILWAYS v. KANLAON CONSTRUCTION ENTERPRISES CO. +

PHILIPPINE NATIONAL RAILWAYS, PETITIONER, VS. KANLAON CONSTRUCTION ENTERPRISES CO., INC., RESPONDENT.

D E C I S I O N

CARPIO, J.:

The Case

This is a petition for review[1] of the 26 February 2008 Decision[2] and 26 May 2008 Resolution[3] of the Court of Appeals in CA-G.R. CV No. 70205. In its 26 February 2008 Decision, the Court of Appeals affirmed the 12 December 2000 Decision,[4] as amended by the 22 February 2001 Order,[5] of the Regional Trial Court of Quezon City, Branch 221 (trial court), directing petitioner Philippine National Railways (PNR) to pay respondent Kanlaon Construction Enterprises Co., Inc. (Kanlaon) the remaining balance of the contracts and to release the retention money. In its 26 May 2008 Resolution, the Court of Appeals denied PNR's motion for reconsideration.

The Facts

In July 1990, PNR and Kanlaon entered into contracts for the repair of three PNR station buildings and passenger shelters, namely: 1) College Station for P2,316,568.41;[6] 2) Biñan Station for P2,547,978.63;[7] and 3) Buendia Station for P1,820,534.40.[8] The total cost of the three projects was P6,685,081.44. By November 1990, Kanlaon alleged that it had already completed the three projects.[9]

On 30 June 1994, Kanlaon sent a demand letter to PNR requesting for the release of the retention money in the amount of P333,894.07.[10]

In a letter dated 12 July 1994,[11] PNR denied Kanlaon's demand because of the 24 January 1994 Notices of Suspension[12] issued by the Commission on Audit (COA).

On 8 November 1994, Kanlaon filed a complaint for collection of sum of money plus damages against PNR.[13] Kanlaon sought to recover from PNR a total of P865,906.79 consisting of the remaining balance of the three projects in the amount of P531,652.72[14] and the retention money in the amount of P334,254.07. In its amended complaint dated 17 August 1995, Kanlaon impleaded the COA.[15]

In its answer, PNR admitted the existence of the three contracts but alleged that Kanlaon did not comply with the conditions of the contract. PNR also alleged that Kanlaon did not complete the projects and that PNR did not have any unpaid balance. PNR added that it had a valid ground to refuse the release of the retention money because of the COA orders suspending the release of payment to Kanlaon.

In its 12 December 2000 Decision, the trial court ruled in favor of Kanlaon. The dispositive portion of the 12 December 2000 Decision reads:

WHEREFORE, premises considered, judgment is hereby rendered in favor of the plaintiff [Kanlaon] and against the herein defendants [PNR and COA]. Accordingly, defendant PNR is ordered to pay the plaintiff the following amount[s]:

1. P333,894.07 representing the unreleased retention money plus legal interest at 12% per annum computed from the date of the first written demand; [and]

2. P531,652.72 representing the unpaid contract price for the completed projects plus legal interest of 12% per annum computed from the date of the first written demand.

Defendant COA is absolved of any liability for actual damages or moral damages.

However, both defendant PNR and defendant COA are solidarily liable for reasonable attorney's fees in the amount of P50,000.00 and cost of suit.

SO ORDERED.[16]

On 28 December 2000, COA appealed. On 9 January 2001, PNR filed a motion for reconsideration.

In its 22 February 2001 Order, the trial court modified its 12 December 2000 Decision and fixed the interest rate from twelve percent to six percent per annum from the date of the first written demand.

PNR and COA appealed to the Court of Appeals.

In its 26 February 2008 Decision, the Court of Appeals affirmed the trial court's 12 December 2000 Decision, as amended by its 22 February 2001 Order.

PNR filed a motion for reconsideration.

In its 26 May 2008 Resolution, the Court of Appeals denied PNR's motion.

The Ruling of the Trial Court

The trial court found that Kanlaon completed the projects and that it was entitled to payment in full of the contract price, as well as the release of the retention money. The trial court declared the PNR ledger, which was the only documentary evidence presented by PNR to show that the projects were not completed, to be self-serving and unverified. The trial court declared that PNR failed to present any credible and substantial evidence that Kanlaon failed to complete the projects. Moreover, the trial court stated that COA suspended payment because PNR failed to comply with certain conditions and not because Kanlaon did not complete the projects. The trial court also took judicial notice of the fact that the PNR stations at College, Biñan and Buendia are fully operational and have been continuously used by PNR and the riding public. The trial court absolved COA from actual and moral damages because there was no contractual relations between COA and Kanlaon and it was not shown that COA acted in bad faith or with malice or gross negligence when it issued the Notices of Suspension.

The Ruling of the Court of Appeals

The Court of Appeals sustained the trial court's ruling that PNR was liable for the remaining balance of the contract price and the retention money. The Court of Appeals agreed with the trial court that the preponderance of evidence leaned in favor of Kanlaon's claim against PNR and that there was nothing on record which supports PNR's allegation that Kanlaon failed to complete the project. The Court of Appeals said the only reason PNR refused to pay Kanlaon was because of COA's Notices of Suspension and not Kanlaon's non-completion of the projects. However, the Court of Appeals held that COA is not liable for attorney's fees and costs of the suit for lack of factual and legal bases.

The Issues

PNR raises the following issues:

I. The Court of Appeals erred in finding that the projects were completed.

II. The Court of Appeals erred in affirming the 12 December 2000 Decision of the trial court, as modified by the Order dated February 22, 2001.

III. The Court of Appeals erred in ruling that interest should be reckoned from the date of respondent's first written demand.[17]

The Ruling of the Court


The petition is meritorious.

The Court notes that one of the reasons the COA issued the Notices of Suspension was because the contracts did not contain a Certificate of Availability of Funds as required under Sections 85 and 86 of Presidential Decree No. 1445.[18] Kanlaon does not dispute the absence of a Certificate of Availability of Funds.

The Administrative Code of 1987, a more recent law, also contains the same provisions. Sections 46, 47, and 48, Chapter 8, Subtitle B, Title I, Book V of the Administrative Code of 1987 provide:

SECTION 46. Appropriation Before Entering into Contract. --

1. No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure; and

2. Notwithstanding this provision, contracts for the procurement of supplies and materials to be carried in stock may be entered into under regulations of the Commission provided that when issued, the supplies and materials shall be charged to the proper appropriations account.

SECTION 47. Certificate Showing Appropriation to Meet Contract. -- Except in the case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three (3) months, or banking transactions of government-owned or controlled banks, no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and that the amount necessary to cover the proposed contract for the current calendar year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certificate signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished.

SECTION 48. Void Contract and Liability of Officer. -- Any contract entered into contrary to the requirements of the two (2) immediately preceding sections shall be void, and the officer or officers entering into the contract shall be liable to the Government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties. (Emphasis supplied)

Thus, the Administrative Code of 1987 expressly prohibits the entering into contracts involving the expenditure of public funds unless two prior requirements are satisfied. First, there must be an appropriation law authorizing the expenditure required in the contract. Second, there must be attached to the contract a certification by the proper accounting official and auditor that funds have been appropriated by law and such funds are available. Failure to comply with any of these two requirements renders the contract void.

In several cases,[19] the Court had the occasion to apply these provisions of the Administrative Code of 1987 and the Government Auditing Code of the Philippines. In these cases, the Court clearly ruled that the two requirements - the existence of appropriation and the attachment of the certification - are "conditions sine qua non for the execution of government contracts."

In COMELEC v. Quijano-Padilla,[20] we stated:

It is quite evident from the tenor of the language of the law that the existence of appropriations and the availability of funds are indispensable pre-requisites to or conditions sine qua non for the execution of government contracts. The obvious intent is to impose such conditions as a priori requisites to the validity of the proposed contract.[21]

The law expressly declares void a contract that fails to comply with the two requirements, namely, an appropriation law funding the contract and a certification of appropriation and fund availability.[22] The clear purpose of these requirements is to insure that government contracts are never signed unless supported by the corresponding appropriation law and fund availability.[23]

The three contracts between PNR and Kanlaon do not comply with the requirement of a certification of appropriation and fund availability. Even if a certification of appropriation is not applicable to PNR if the funds used are internally generated, still a certificate of fund availability is required. Thus, the three contracts between PNR and Kanlaon are void for violation of Sections 46, 47, and 48, Chapter 8, Subtitle B, Title I, Book V of the Administrative Code of 1987, as well as Sections 85, 86, and 87 of the Government Auditing Code of the Philippines.

However, Kanlaon is not left without recourse. The law itself affords it the remedy. Section 48 of the Administrative Code of 1987 provides that "the officer or officers entering into the contract shall be liable to the Government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties."[24] Kanlaon could go after the officers who signed the contract and hold them personally liable.

WHEREFORE, we GRANT the petition. We REVERSE and SET ASIDE the 26 February 2008 Decision and 26 May 2008 Resolution of the Court of Appeals in CA-G.R. CV No. 70205.

SO ORDERED.

Peralta, Abad, and Mendoza,  JJ., concur.
Sereno,* J., please see also concurring opinion.



* Designated additional member per Special Order No. 978 dated 30 March 2011.

[1] Under Rule 45 of the Rules of Court.

[2] Rollo, pp. 58-68. Penned by Associate Justice Sesinando E. Villon, with Associate Justices Martin S. Villarama, Jr. (now a member of this Court) and Mario L. Guariña III, concurring.

[3] Id. at 73.

[4] Id. at 44-51. Penned by Judge Noel G. Tijam (now an Associate Justice of the Court of Appeals).

[5] Id. at 57.

[6] Id. at 18-20. The contract was dated 12 July 1990.

[7] Id. at 21-23. The contract was dated 19 July 1990.

[8] Id. at 24-26. The contract was dated 19 July 1990.

[9] Kanlaon alleged that it completed the College Station on 23 November 1990, the Biñan Station on 19 November 1990, and the Buendia Station on 12 November 1990.

[10] Records, p. 17.

[11] Id. at 19.

[12] Id. at 32-40. The COA directed PNR to suspend the payment due to Kanlaon for the following reasons:

1. The contracts were not approved by the PNR Board of Directors pursuant to Executive Order No. 164, as amended by Executive Order No. 380;

2. The contracts were not submitted to the COA for review in accordance with COA Circular No. 89-299;

3. The contracts did not contain a Certificate of Availability of Funds as required under Sections 85 and 86 of P.D. 1445; and

4. No request for inspection of work accomplishment was made.

[13] Id. at 1-7.

[14] Kanlaon claimed that PNR had the following remaining balance on the three projects: College Station at P131,962.65; Biñan Station at P141,391.89; and Buendia Station at P288,298.18.

[15] Rollo, pp. 35-43.

[16] Id. at 51.

[17] Id. at 12.

[18] Entitled "Ordaining and Instituting a Government Auditing Code of the Philippines." Also known as the "Government Auditing Code of the Philippines." Dated 11 June 1978. Sections 85 and 86 of P.D. 1445 provides:

Section 85. Appropriation before entering into contract.

1. No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure.

2. Notwithstanding this provision, contracts for the procurement of supplies and materials to be carried in stock may be entered into under regulations of the Commission provided that when issued, the supplies and materials shall be charged to the proper appropriation account.

Section 86. Certificate showing appropriation to meet contract. Except in the case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three months, or banking transactions of government-owned or controlled banks no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certificate signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished.

[19] COMELEC v. Quijano-Padilla, 438 Phil. 72 (2002); Agan, Jr. v. Phil. International Air Terminals Co., Inc., 450 Phil. 744 (2003); and Osmeña v. Commission on Audit, G.R. No. 98355, 2 March 1994, 230 SCRA 585.

[20] 438 Phil. 72 (2002).

[21] Id. at 93-94.

[22] Section 48, Chapter 8, Subtitle B, Title I, Book V of the Administrative Code of 1987 and Section 87 of the Government Auditing Code of the Philippines.

[23] Melchor v. Commission on Audit, G.R. No. 95398, 16 August 1991, 200 SCRA 704.

[24] See also Section 87 of the Government Auditing Code of the Philippines.




CONCURRING OPINION


SERENO, J.:

I fully agree that contracts of government agencies without the proper appropriation and the accompanying Certificate of Availability of Funds are void for being contrary to law. In the case of government corporations, of course, the first requirement is not imposable. However, it must be noted that this rule notwithstanding, recovery for unpaid services or sale of goods may still be had, as we enunciated in Vigilar v. Aquino,[1] Royal Trust Corporation v. COA,[2] Eslao v. COA,[3] Melchor v. COA,[4] EPG Construction Company v. Vigilar,[5] and Department of Health v. C.V. Canchela & Associates, Architects.[6]  Public interest and equity may dictate that the contractor should be compensated for services rendered and work done that benefited the government and the public.[7]  In the instant case, considering that respondent has already been paid the equivalent of around eighty seven (87%) percent of the total contract price, the application of equity principles do not seem to be as imperative as in the cases earlier cited.  There is no reason to remand the case for reception of evidence to determine quantum meruit, which is the default solution when the contract supporting the services rendered has been declared void.  Had payment to respondent been significantly less as to amount to unjust enrichment on the part of government, I may have had to disagree with the ponencia.



[1] G.R. No. 180388, January 18, 2011.

[2] Supreme Court Resolution En Banc, G.R. No. 84202, November 22, 2988, cited in Eslao v. COA, 195 SCRA 730.

[3] G.R. No. 89745, April 8, 1991, 195 SCRA 730.

[4] G.R. No. 95938, August 16, 1991, 200 SCRA 705.

[5] G.R. No. 131544, March 16, 2001, 354 566.

[6] Supra at note 7.

[7] Vigilar v. Aquino, G.R. No. 180388, January 18, 2011.