THIRD DIVISION

[ G.R. No. 211504, March 08, 2017 ]

FEDERAL BUILDERS v. POWER FACTORS +

FEDERAL BUILDERS, INC., PETITIONER, VS. POWER FACTORS, INC., RESPONDENT.

D E C I S I O N

BERSAMIN, J.:

An agreement to submit to voluntary arbitration for purposes of vesting jurisdiction over a construction dispute in the Construction Industry Arbitration Commission (CIAC) need not be contained in the construction contract, or be signed by the parties. It is enough that the agreement be in writing.

The Case

Federal Builders Inc. (Federal) appeals to reverse the decision promulgated on August 12, 2013,[1] whereby the Court of Appeals (CA) affirmed the adverse decision rendered on May 12, 2010 by the Construction Industry Arbitration Commission (CIAC) with modification of the total amount awarded.[2]

Antecedents

Federal was the general contractor of the Bullion Mall under a construction agreement with Bullion Investment and Development Corporation (BIDC). In 2004, Federal engaged respondent Power Factors Inc. (Power) as its subcontractor for the electric works at the Bullion Mall and the Precinct Building for P18,000,000.00.[3]

On February 19, 2008, Power sent a demand letter to Federal claiming the unpaid amount of P11,444,658.97 for work done by Power for the Bullion Mall and the Precinct Building. Federal replied that its outstanding balance under the original contract only amounted to P1,641,513.94, and that the demand for payment for work done by Power after June 21, 2005 should be addressed directly to BIDC.[4] Nonetheless, Power made several demands on Federal to no avail.

On October 29, 2009, Power filed a request for arbitration in the CIAC invoking the arbitration clause of the Contract of Service reading as follows:
15. ARBITRATION COMMITTEE - All disputes, controversies or differences, which may arise between the parties herein, out of or in relation to or in connection with this Agreement, or for breach thereof shall be settled by the Construction Industry Arbitration Commission (CIAC) which shall have original and exclusive jurisdiction over the aforementioned disputes.[5]
On November 20, 2009, Atty. Vivencio Albano, the counsel of Federal, submitted a letter to the CIAC manifesting that Federal agreed to arbitration and sought an extension of 15 days to file its answer, which request the CIAC granted.

On December 16, 2009, Atty. Albano filed his withdrawal of appearance stating that Federal had meanwhile engaged another counsel.[6]

Federal, represented by new counsel (Domingo, Dizon, Leonardo and Rodillas Law Office), moved to dismiss the case on the ground that CIAC had no jurisdiction over the case inasmuch as the Contract of Service between Federal and Power had been a mere draft that was never finalized or signed by the parties. Federal contended that in the absence of the agreement for arbitration, the CIAC had no jurisdiction to hear and decide the case.[7]

On February 8, 2010, the CIAC issued an order setting the case for hearing, and directing that Federal's motion to dismiss be resolved after the reception of evidence of the parties.[8]

Federal did not thereafter participate in the proceedings until the CIAC rendered the Final Award dated May 12, 2010,[9] disposing:
In summary: Respondent Federal Builders, Inc. is hereby ordered to pay claimant Power Factors, Inc. the following sums:

1. Unpaid balance on the original contract
P4,276,614.75;
 
2. Unpaid balance on change order nos. 1, 2, 3, 4, 5, 6, 7, 8, & 9
3,006,970.32;
 
3. Interest to May 13, 2010
1,686,149.94;
 
4. Attorney's Fees
250,000.00;
 
5. Cost of Arbitration
149,503.86;
 
 
 
 
P9,369,238.87
 
The foregoing amount shall earn legal interest at the rate of 6% per annum from the date of this Final Award until this award becomes final and executory, Claimant shall then be entitled to 12% per annum until the entire amount is fully satisfied by Respondent.

Federal appealed the award to the CA insisting that the CIAC had no jurisdiction to hear and decide the case; and that the amounts thereby awarded to Power lacked legal and factual bases.

On August 12, 2013, the CA affirmed the CIAC's decision with modification as to the amounts due to Power,[10] viz.:
WHEREFORE, the CIAC Final Award dated 12 May 2010 in CIAC Case No. 31-2009 is hereby AFFIRMED with MODIFICATION.

As modified, FEDERAL BUILDERS, INC. is ordered to pay POWER FACTORS, INC. the following:
1. Unpaid balance on the original contract
P4,276,614.75;
 
   
2. Unpaid balance on change orders
2,864,113.32;
 
   
3. Attorney's Fees
250,000.00;
 
   
4. Cost of Arbitration
149,503.86;
 
The interest to be imposed on the net award (unpaid balance on the original contract and change order) amounting to P7,140,728.07 awarded to POWER FACTORS INC. shall be six (6%) per annum, reckoned from 4 July 2006 until this Decision becomes final and executory. Further, the total award due to POWER FACTORS INC. shall be subjected to an interest of twelve percent (12%) per annum computed from the time this judgment becomes final and executory, until full satisfaction.

SO ORDERED.[11]
Anent jurisdiction, the CA explained that the CIAC Revised Rules of Procedure stated that the agreement to arbitrate need not be signed by the parties; that the consent to submit to voluntary arbitration was not necessary in view of the arbitration clause contained in the Contract of Service; and that Federal's contention that its former counsel's act of manifesting its consent to the arbitration stipulated in the draft Contract of Service did not bind it was inconsequential on the issue of jurisdiction.[12]

Concerning the amounts awarded, the CA opined that the CIAC should not have allowed the increase based on labor-cost escalation because of the absence of the agreement between the parties on such escalation and because there was no authorization in writing allowing the adjustment or increase in the cost of materials and labor.[13]

After the CA denied Federal's motion for reconsideration on February 19, 2004,[14] Federal has come to the Court on appeal.

Issue

The issues to be resolved are: (a) whether the CA erred in upholding CIAC's jurisdiction over the present case; and (b) whether the CA erred in holding that Federal was liable to pay Power the amount of P7,140,728.07.

Ruling of the Court

The appeal is bereft of merit.

1.

The parties had an effective agreement to submit to voluntary arbitration; hence, the CIAC had jurisdiction


The need to establish a proper arbitral machinery to settle disputes expeditiously was recognized by the Government in order to promote and maintain the development of the country's construction industry. With such recognition came the creation of the CIAC through Executive Order No. 1008 (E.O. No. 1008), also known as The Construction Industry Arbitration Law. Section 4 of E.O. No. 1008 provides:
Sec. 4. Jurisdiction. — The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration. x x x
Under the CIAC Revised Rules of Procedure Governing Construction Arbitration (CIAC Revised Rules), all that is required for the CIAC to acquire jurisdiction is for the parties of any construction contract to agree to submit their dispute to arbitration.[15] Also, Section 2.3 of the CIAC Revised Rules states that the agreement may be reflected in an arbitration clause in their contract or by subsequently agreeing to submit their dispute to voluntary arbitration. The CIAC Revised Rules clarifies, however, that the agreement of the parties to submit their dispute to arbitration need not be signed or be formally agreed upon in the contract because it can also be in the form of other modes of communication in writing, viz.:
RULE 4 - EFFECT OF AGREEMENT TO ARBITRATE

SECTION 4.1. Submission to CIAC jurisdiction - An arbitration clause in a construction contract or a submission to arbitration of a construction dispute shall be deemed an agreement to submit an existing or future controversy to CIAC jurisdiction, notwithstanding the reference to a different arbitration institution or arbitral body in such contract or submission.

4.1.1 When a contract contains a clause for the submission of a future controversy to arbitration, it is not necessary for the parties to enter into a submission agreement before the Claimant may invoke the jurisdiction of CIAC.

4.1.2 An arbitration agreement or a submission to arbitration shall be in writing, but it need not be signed by the parties, as long as the intent is clear that the parties agree to submit a present or future eontroversy arising from a construction contract to arbitration. It may be in the form of exchange of letters sent by post or by telefax, telexes, telegrams, electronic mail or any other mode of communication.
The liberal application of procedural rules as to the form by which the agreement is embodied is the objective of the CIAC Revised Rules. Such liberality conforms to the letter and spirit of E.O. No. 1008 itself which emphasizes that the modes of voluntary dispute resolution like arbitration are always preferred because they settle disputes in a speedy and amicable manner. They likewise help in alleviating or unclogging the judicial dockets. Verily, E.O. No. 1008 recognizes that the expeditious resolution of construction disputes will promote a healthy partnership between the Government and the private sector as well as aid in the continuous growth of the country considering that the construction industry provides employment to a large segment of the national labor force aside from its being a leading contributor to the gross national product.[16]

Worthy to note is that the jurisdiction of the CIAC is over the dispute, not over the contract between the parties.[17] Section 2.1, Rule 2 of the CIAC Revised Rules particularly specifies that the CIAC has original and exclusive jurisdiction over construction disputes, whether such disputes arise from or are merely connected with the construction contracts entered into by parties, and whether such disputes arise before or after the completion of the contracts. Accordingly, the execution of the contracts and the effect of the agreement to submit to arbitration are different matters, and the signing or non-signing of one does not necessarily affect the other. In other words, the formalities of the contract have nothing to do with the jurisdiction of the CIAC.

Federal contends that there was no mutual consent and no meeting of the minds between it and Power as to the operation and binding effect of the arbitration clause because they had rejected the draft service contract.

The contention of Federal deserves no consideration.

Under Article 1318 of the Civil Code, a valid contract should have the following essential elements, namely: (a) consent of the contracting parties; (b) object certain that is the subject matter of the contract; and (c) cause or consideration. Moreover, a contract does not need to be in writing in order to be obligatory and effective unless the law specifically requires so.

Pursuant to Article 1356[18] and Article 1357[19] of the Civil Code, contracts shall be obligatory in whatever form they may have been entered into, provided that all the essential requisites for their validity are present. Indeed, there was a contract between Federal and Power even if the Contract of Service was unsigned. Such contract was obligatory and binding between them by virtue of all the essential elements for a valid contract being present.

It clearly appears that the works promised to be done by Power were already executed albeit still incomplete; that Federal paid Power P1,000,000.00 representing the originally proposed downpayment, and the latter accepted the payment; and that the subject of their dispute concerned only the amounts still due to Power. The records further show that Federal admitted having drafted the Contract of Services containing the following clause on submission to arbitration, to wit:
15. ARBITRATION COMMITTEE - All disputes, controversies or differences, which may arise between the Parties herein, out of or in relation to or in connection with this Agreement, or for breach thereof shall be settled by the Construction Industry Arbitration Commission (CIAC) which shall have original and exclusive jurisdiction over the aforementioned disputes.[20]
With the parties having no issues on the provisions or parts of the Contract of Service other than that pertaining to the downpayment that Federal was supposed to pay, Federal could not validly insist on the lack of a contract in order to defeat the jurisdiction of the CIAC. As earlier pointed out, the CIAC Revised Rules specifically allows any written mode of communication to show the parties' intent or agreement to submit to arbitration their present or future disputes arising from or connected with their contract.

The CIAC and the CA both found that the parties had disagreed on the amount of the downpayment. On its part, Power indicated after receiving and reviewing the draft of the Contract of Service that it wanted 30% as the downpayment. Even so, Power did not modify anything else in the draft, and returned the draft to Federal after signing it. It was Federal that did not sign the draft because it was not amenable to the amount as modified by Power. It is notable that the arbitration clause written in the draft of Federal was unchallenged by the parties until their dispute arose.

Moreover, Federal asserted the original contract to support its claim against Power. If Federal would insist that the remaining amount due to Power was only P1,641,513.94 based on the original contract,[21] it was really inconsistent for Federal to rely on the draft when it is beneficial to its side, and to reject its efficacy and existence just to to relieve itself from the CIAC's unfavorable decision.

The agreement contemplated in the CIAC Revised Rules to vest jurisdiction of the CIAC over the parties' dispute is not necessarily an arbitration clause to be contained only in a signed and finalized construction contract. The agreement could also be in a separate agreement, or any other form of written communication, as long as their intent to submit their dispute to arbitration is clear. The fact that a contract was signed by both parties has nothing to do with the jurisdiction of the CIAC, and this is the explanation why the CIAC Revised Rules itself expressly provides that the written communication or agreement need not be signed by the parties.

Although the agreement to submit to arbitration has been expressly required to be in writing and signed by the parties therein by Section 4[22] of Republic Act No. 876 (Arbitration Law),[23] the requirement is conspicuously absent from the CIAC Revised Rules, which even expressly allows such agreement not to be signed by the parties therein.[24] Brushing aside the obvious contractual agreement in this case warranting the submission to arbitration is surely a step backward.[25] Consistent with the policy of encouraging alternative dispute resolution methods, therefore, any doubt should be resolved in favor of arbitration.[26] In this connection, the CA correctly observed that the act of Atty. Albano in manifesting that Federal had agreed to the form of arbitration was unnecessary and inconsequential considering the recognition of the value of the Contract of Service despite its being an unsigned draft.

2.

Amounts as modified by the CA are correct


We find no reversible error regarding the amounts as modified by the CA. Power did not sufficiently establish that the change or increase of the cost of materials and labor was to be separately determined and approved by both parties as provided under Article 1724 of the Civil Code. As such, Federal should not be held liable for the labor cost escalation.

WHEREFORE, the Court AFFIRMS the decision promulgated on August 12, 2013; and ORDERS the petitioner to pay the costs of suit.

SO ORDERED.

Velasco, Jr., (Chairperson), Reyes, Jardeleza, and Caguioa,* JJ., concur.


* Designated as additional Member of the Third Division per Special Order No. 2417 dated January 4, 2017.

[1] Rollo, pp. 32-45; penned by Associate Justice Leoncia R. Dimagiba and concurred in by Associate Justice Rosmari D. Carandang and Associate Justice Ricardo R. Rosario.

[2] Id. at 98-128.

[3] Id. at 33.

[4] Id.

[5] Id. at 44.

[6] Id. at 34-35.

[7] Id. at 35.

[8] Id.

[9] Supra note 2.

[10] Supra note 1.

[11] Id. at 44-45.

[12] Id. at 38.

[13] Id. at 42-43.

[14] Rollo, p. 47.

[15] Rule 4, CIAC Revised Rules; LICOMCEN, Inc. v. Foundation Specialists, Inc., G.R. Nos. 167022 & 169678, April 4, 2011, 647 SCRA 83, 97.

[16] Sec perambulatory clauses of E.O. No. 1008.

[17] National Irrigation Administration v. Court of Appeals, G.R. No. 129169, November 17, 1999, 318 SCRA 255, 269.

[18] Article 1356. Contracts shall be obligatory, in whatever form they may have been entered into, provided all the essential requisites for their validity are present. However, when the law requires that a contract be in some form in order that it may be valid or enforceable, or that a contract be proved in a certain way, that requirement is absolute and indispensable. In such cases, the right of the parties stated in the following article cannot be exercised.

[19] Article 1357. If the law requires a document or other special form, as in the acts and contracts enumerated in the following article, the contracting parties may compel each other to observe that form, once the contract has been perfected. This right may be exercised simultaneously with the action upon the contract.

[20] Rollo, p. 34.

[21] Id.

[22] Section 4. Form of arbitration agreement. - A contract to arbitrate a controversy thereafter arising between the parties, as well as a submission to arbitrate an existing controversy, shall be in writing and subscribed by the party sought to be charged, or by his lawful agent.

The making of a contract or submission for arbitration described in section two hereof, providing for arbitration of any controversy, shall be deemed a consent of the parties of the province or city where any of the parties resides, to enforce such contract of submission.

[23] An Act to Authorize the Making of Arbitration and Submission Agreements, to Provide for the Appointment of Arbitrators and the Procedure for Arbitration in Civil Controversies, and for Other Purposes; June 19, 1953.

[24] Subsection 4.1.2, Rule 4 of the CIAC Revised Rules.

[25] LM Power Engineering Corporation v. Capitol Industrial Construction Groups, Inc., G.R. No. 141833, March 26, 2003, 399 SCRA 562, 569.

[26] Id. at 570.