[ LETTER OF INSTRUCTIONS NO. 1060, September 02, 1980 ]

TO:
Presidential Committee for Rehabilitation
and Development of Southern Philippines
Southern Philippines Development Authority
The ministry of the Budget
All Agencies Concerned

WHEREAS, the Presidential Committee for Rehabilitation and Development. of Southern Philippines created under MON. 697 has identified a number of projects with, high economic value, social productivity and ecological/energy significance in Region XII and elsewhere in Southern Philippines;

WHEREAS, these projects, now referred to as Project "Ranaw" (Maranaw for Lake), have for their goals the generation of more income and employment to the people, environmental, tourism and energy development, and increase of production and productivity in the Lake Lanao watershed area; and

WHEREAS, in order to maximize the potentials of the programs and projects there is the need to provide adequate organizational and resource support to Project "Ranaw" in line with the revitalized program thrusts and strategies of the Government in Southern Philippines.

NOW, THEREFORE, I, FERDINAND E. MARCOS, President of the Philippines, do hereby direct as follows:
  1. Without prejudice to the subsequent listing and/or identification of related projects by the" PCRDSP under Project "Ranaw", the attached list of projects (indicating also the participating agencies as well as their tasks) shall be considered as priority under the PCRDSP program insofar as the Lake Lanao/Agus watershed influence area is concerned;

  2. In the identification, mobilization and management of projects, the following policies, terms of reference and guidelines shall be observed as much, as possible;

    a) The agency or units thereof listed first shall be the lead agency and is authorized to call on concerned agencies or instrumentalities of Government (whether national or local) for data, assistance and linkages.

    b) The lead agency shall principally contribute/appropriate the necessary funds as per project requirement.

    The participating/involved agencies shall provide funds in a secondary role.  All funds shall be chargeable to the agency/office's current budget and/or obligated allotments, balances or savings and other sources.  In cases where additional funds are needed, special budgets shall be submitted to the President of tho Philippines thru the PCRDSP.

    c) A project management team shall be organized immediately from amongst the represented agencies to be headed/coordinated by the identified lead agency.

    d) The views, recommendations and/or participation of the private capital, management, industrial, civic and other sectors shall be considered in all aspects of the projects insofar as these are deemed beneficial to said projects.

  3. The Executive Committee of the PCRDSP shall determine the project timetables in consultation with involved agencies.

  4. The sum of One Million Pesos (P1,000,000.00) is hereby authorized to be released to the PCRDSP through the Southern Philippines Development Authority from the Special Activities Fund which shall be used principally as support fund for project pre-operation and monitoring activities.

    This Letter of Instructions shall take effect immediately.
DONE in the City of Manila,this 2nd day of September, in the year of Our Lord, Nineteen hundred and eighty.

(Sgd.) FERDINAND E. MARCOS
President of the Philippines

All Concerned
01 August 1980
Subject: Implementing Instructions/Schedules for
Project "Ranao", PCRSP
   
     
Projects/Launching
Agencies
Tasks/Reponsibilities
       
1. Lanao Sur
(August 14, 1980)
MSU/COF Technology
       
2. Fishmeal-Marawi
City (Sept. 11/80
PCRDSP
MSU/COF
Funding./Management
Technology/Funding
Facilities
       
    BLISSMARX
SPDA
MOE/BED
Marketing support
Marketing
Equipment
       
3. Compact Vegetables
Farms-Guimba,
Marawi City
Bayog/Mandulog,
Iligan (Sept. 11, 1980)
PCRDSP
Iligan City &
Marawi City
MOA
BLISSMARK
PAB
Funding/Management
Funding/Land

Technology
Marketing support
Financing
       
4. Roof Tiles-Iligan
City & Marawi City
(October 1980)
SPDA
PCRDSP
MSU
Iligan City &
Marawi City
BLISSMARK
PAB
Funding/Management
Funding
Facilities/Technology
Funding (contribution)
Land/Raw Materials
Marketing
Financing
       
5. Coconut Central
Pilot Plant
Iligan City
April 1981)
MSU-IIT

SPDA
PCA
NSDB
TRCFI
Iligan City
DBP
Funding/Management/
Technology/Facilities
Funding /Marketing
Funding /Technology
Funding /Technology
Funding /Technology
Land
Financing
       
6. Dairy Farm -
Iligan City and
Baloi, Lanao Norte
(December 1980)
SPDA
MOA
MSU
BLISSMARK
MND/AFP
DBP
PAB
Funding /Management
Funding /Technology
Funding /Technology
Marketing
Security
Financing
Financing
       
       
All Concerned
01 August 1980
Subject: Implementing Instructions/Schedules for
Project "Ranao", PCRSP
 
Projects/Launching
Agencies
Tasks/Reponsibilities
       
b) Tourism / Beautification    
       
7. Marawi Resort Inc.
Marawi City
(Sept. 21, 1980)
SPDA
MSU
MOT/PTA

FTI/MGA
MLGCD
Funding/Management
Land/Lingkages
Technical/Assistance/
Additional Facilities
Kadiwa
Kadiwa
       
8. Public Beaches -
Maranto, Lanao
Sur, Balindong
Lanao Sur, Marawi
City, Iligan City
Kolambugan, Lanao
Norte (October
1980 )
MOT/PTA

Provincial
City/Municipal
Gov't.
MSU/CHARM
MPH
MND/AFP
Funding/Technical
Assistance/Management
Funding/Land/Lingkages


Technical Assistance
Access Roads
Security
       
9. Coves Development -
Mbolong and
Kaloocan, Marawi
City (November
1980 )
MOT/PTA

MPW

MSU
MPH
Marawi City
Funding/Technical/Assistance/
Management
Technical Assistance/
Equipment
Technical Assistance
Access Roads
Funding/Land/Lingkages
       
10. Springs Dev't
Matampay, Marawi
City (January
1981)
MOT/PTA
MPW

MPH
MSU
Marawi City
Funding/Management
Funding/Technical
Assistant/ Equipment
Access Roads
Technical Assistance
Land/Lingkages/Funding
       
11. Old City Hall
Marawi City
(November 1980)
MOT/PTA

MPW

MSU
MPH
Marawi City
MND/AFP
Funding/Technical
Assistant/ Equipment
Technical Assistance/
Equipment
Technical Assistance
Access Roads
Linkages
Security
       
All Concerned
01 August 1980
Subject: Implementing Instructions/Schedules for
Project "Ranao", PCRSP
 
Projects/Launching
Agencies
Tasks/Reponsibilities
       
12. Signal Hill -
Marawi City
(July 1981)
MOT/PTA

MPW

MPH
MSU
Marawi City
MND/AFP
Funding/Techinical Assistance/
Management
Technical Assistance/
Equipment
Access Roads
Technical Assistance
Land/Linkages
Secutiry
       
13. Tourist Haven -
Maria Cristina Falls
Iligan City
(Sept. 21, 1981)
MOT/PTA


Iligan City
MPW

MPH
MSU-IIT
MND/AFP
MOE/NPC
Funding/Technical Assistance
(assignment of
a top architect )
Funding/Management
Technical Assistance/
Equipment
Access Roads
Technical Assistance
Security
Funding/Technical Assistance
       
14. City Park -
Iligan City
(July 1980)
Iligan City
MNR/BFD


MOT/PTA

MPH
Funding/Management
Proclamation/Surveys
Delineation/Technical
Assistance
Funding/Technical
Assistance
Access Roads
       
15. National Park -
Maria Cristina Falls
Iligan City
(September 1980)
MNR/BFD

MOE/NPC
Funding/Technical
Assistance/Management
Technical Assistance
       
(c) Watershed:    
       
16. Agro-Forestry Fee
Planting
Lanao Norte
Lanao Sur
Marawi City
Iligan City
(August 14, 1980
MNR/BFD

MOA

MOE/NPC
Provincial/
City/Municipal Govts.
Funding/Technical
Assistance/Management
Funding/Technical
Assistance
Funding
Funding/Linkages
       
17. Agro-Forestry Seedling
Bank
Lanao Sur/Marawi
City
Lanao Norte/
Iligan City
MNR/BFD

MOA

Provincial/
City/
Municipal Govts.
MND/AFP
Funding/Technical
Assistance/Management
Funding.Technical
Assistance
Funding/Linkage

Funding/Technical
Assistance
       
18. Physical Protection -
and Dvelopment
Lanao Sur/Lanao
Norte
MNR/EFD

MOA
MOE/NPC
Funding/Management
Technical Assistance
Technical Assistance
Technical Assistance
(a) Reforestation: Provincial/
City/
Security/Linkages
  18.1 Nursery Operation
18.2 Plantation Operation
Municipal Govts.
MND.AFP

Security/Mobility
       
(b) Physical Protection    
       
  18.3 Foot/Aerial Patrols
18.4 Information Dissemination (November 1980)
   
       
19. Watershed Study
and Development
Planning-Lanao
Sur
Lanao Norte
(Sept. 21, 1980)
MOE/NPC

MNR/BFD
City-Provincial/
Municipal
Govts.
MND/AFP
Funding/Technical
Assistance/Management
Technical/Assistance
Security/Linkages/
Mobility

Security/Mobility
       
20. Dredging of Lake
Lanao Sur (1981)
MPW
MOE/NPC
Funding/Management
Technical Support
       
d) Infrastructure    
       
21. Improvement of
Lake Lanao
Circumferential Road
NPH Funding/Management
       
C. In the identification, mobilization and management of projects, the following guidelines, policies and terms of reference shall be observed as much as it is practicable:
       
  1.0
The agency/ministry/instrumentality of the Government or units thereof listed first shall be the lead agency and is authorized to call on agencies concenrned above-listed or not listed for assistance, dara and linkages.
   
  2.0
The lead agency/ministry shall principally contribute/ appropriate the necessary funds as per project requirement. The participating agencies shall provide funds in a secondary role. All funds shall be chargeable against the agency/ministry's current budget. In cases where additional funds are needed, special budgets shall be submitted to the President of the Philippines thru the PCRDSP.
   
  3.0
A project development and/or management team shall be organized immediately from amongst the represented agencies to be chaired by the identified lead agency.
   
  4.0
The views, reconnsdatiors and participation of the private capital, management, civic and marketing sectors shall be considered in all aspects of the projects insofar as these are beneficial to said projects.
   
  5.0
Weekly, bi-weekly and monthly reports or whenever required shall be submitted to the PCRDSP containing confirmation on status, accomplishments, financial statements or such other data or projects performance indicators.


For compliance.

(Sgd.) IMELDA ROMUALDEZ MARCOS