[ DOE CIRCULAR NO. 95-04-002, April 10, 1995 ]
DIRECT SUPERVISION OVER THE ACTIVITIES AND OPERATIONS OF GEOTHERMAL SERVICE CONTRACTORS (GSC)
WHEREAS, in order to effectively supervise and monitor the activities and operations of GSC, there is a need for the registration of sub-contract agreements entered into by and between the GSC and the sub-contractor.
NOW, THEREFORE, to effectively implement Section 1 of P.D. 1442, this circular is hereby issued to read as follows:
SECTION 1. All Geothermal Service Contractors are hereby required to register with the Department of Energy all existing sub-contract agreements not later than May 31, 1995.
SECTION 2. All future sub-contract agreements shall be registered with the DOE within one (1) month from its execution thereof.
SECTION 3. Failure on the part of the Geothermal Service Contractors to register sub-contracting agreements to the DOE shall be sufficient cause to disallow any claim for recovery of expenses incurred from such sub-contracting agreements.
SECTION 4. This Circular shall take effect immediately.
Adopted: 10 Apr. 1995
(SGD.) FRANCISCO L. VIRAY
Acting Secretary