[ PPA ADMINISTRATIVE ORDER NO. 06-95, December 04, 1995 ]

LIBERALIZED REGULATIONS ON PRIVATE PORTS CONSTRUCTION, DEVELOPMENT AND OPERATION



Pursuant to Section 2 (a), (b), Art. II, Section 6 (a) (iii), (iv), (vi), (vii) Art. IV and Section 26 (a) Article VIII of PD 857, the revised Charter of PPA, as amended, as well as relevant provisions of Commonwealth Act 141, and in order to ensure coordination in the processing of applications to develop, construct and operate private ports, the following guidelines are hereby prescribed for the information of and compliance of all concerned.

ARTICLE I

Preliminary Provisions

SECTION 1. Scope - This Order shall apply to all parties seeking for clearance to develop, permit to construct and/or operate a private port facility. It shall also specify the roles of PPA units and offices concerned in the processing, evaluation and approval of these applications.

SECTION 2. Definition of Terms - For purposes of this Order, the following terms used herein shall be construed to mean as indicated:

2.1 Port Zone - An area proclaimed by the President for use as a port pursuant to PD 857.

2.2 Foreshore - That part of the land immediately in front of the shore which is between high and low watermarks, and alternately covered with water and left dry by the flux and reflux of the tides and not located in a port zone. It is indicated by the middle line between the highest and lowest tides.

2.3 Foreshore Lease Agreement for Pier Purposes - A contract of lease of a foreshore and offshore area of the purpose of constructing and operating a private port granted by the Department of Environment and Natural Resources (DENR) thru the Land Management Bureau, for a period of not more than twenty-five (25) years, renewable for another period not exceeding twenty five (25) years, at the option of the Lessor, subject to existing laws and regulations.

2.4 Private Port - A port facility constructed and owned by a private person or entity as authorized by the government. It is classified according to the nature of its operation and purpose, thus:

2.4.1 Private Non-Commercial Port - A port facility constructed along the seacoast and owned by a private person or entity as a component of or accessory to its own business or principal economic activity and which does not offer port services to the general public but exists generally for its own particular use and need. Its use by third party users is only incidental to its operation of the port in view of the availability of specialized and dedicated cargo handling gears and equipment used to handle, usually homogenous cargo, unique to the private port facility, and conducted on a limited and non-commercial basis.

2.4.2 Private Commercial Port - A port facility constructed along the seacoast and owned by a private person or entity which offers, as its principal business activity, port services to the general port users. The operation of the port facility is not a mere component of the main business or activity of the owner or operator, but is the main business activity itself.

2.4.3 Private River Port - A private port located along a river bank.

2.4.4 Marina - A private non-commercial port constructed for the exclusive use of securing motorboats and yacths

SECTION 3. General Policy Statements -

3.1 Subject only to the requirements of national security and public safety and this regulations, the development and operation of private ports is hereby encouraged.

3.2 A private port facility may be established upon approval of the general proposal to develop such private port facility from the PPA. Private river ports, private non-commercial ports, and Marina/s may be allowed construction at the level of the General Manager, while all others will be subject to PPA Board approval.

3.3 The Certificate of Registration/Permit to Operate a private port facility shall be given a period of twenty-five (25) years but not to exceed the term of its foreshore lease contract. This may be renewable for another 25 years but co-terminus with the renewed foreshore lease contract agreement; provided, however, that in case of non-renewal, cancellation, or expiration of the foreshore lease contract, the private port facility or structure thus built on the foreshore and other government owned land utilized for such private port operation, shall become the property of the Authority, free from all liens and encumbrances, unless such foreshore area has been authorized to be reclaimed and the corresponding land has become officially titled to the private port owner concerned.

3.4 Port facilities with expired private port contracts may be leased out again to previous owners/operators.

3.5 The Certificate of Registration/Permit to Operate issued by the Authority shall authorize the holder to operate the private port for the duration specifically indicated in it.

ARTICLE II

Procedures

SECTION 4. Criteria for Evaluation - As a general rule, all applications for the development, construction and operation of private ports shall be granted subject to compliance with this Order and other government laws and regulations.

However, applications for private commercial ports shall have a minimum investment of at least one (1) concrete berth with a minimum length of 65 meters and a draft of at least 5 meters at mean lower low water (mllw).

For reference purposes the application shall include a summary of the following:

4.1 Site/location/distance/accessibility of applied foreshore area from other ports/public utilities and infrastructures;

4.2 Project scope, description, and technical specifications;

4.3 General port lay-out plan and development plan;

4.4 Company profile.

SECTION 5. Clearance to Develop a Private Port Facility -

5.1 The private port investor or owner shall file his formal letter of intent, in triplicate copies, with the Port Management Office concerned where the foreshore area is located, together with the additional requirements as contained in Annex 1* herein incorporated.

5.2 Upon receipt of completed documents, the Responsibility Centers (RCs) concerned shall act on the proposal as follows:

5.2.1 Port Management Office (PMO) - Evaluates, within two weeks from receipt of complete documents, and indorses proposal for approval, unless national security or safety is affected. Informs applicant on the PPA long range plans in the area. Issues to the applicant a Certification that the PMO interposes no objection to the proposed port development, for the latter ™s presentation to DENR in securing a foreshore lease contract. Elevates the proposal to PDO/HO with his recommendation.

5.2.2 Port District Office (PDO) - Validates, within two weeks from receipt, the initial findings and recommendations of the Port Manager, reflecting its concurrence to such proposal and endorses the same to the Office of the AGM Operations, Attention: Commercial Services Department. Retains copy.

5.2.3 Commercial Services Department (CSD) -

5.2.3.1 Processes within four weeks from receipt of complete documents, the private port proposal.

5.2.3.2 Notifies the applicant of denial of proposal if deemed prejudicial to national security or safety. Otherwise prepares an executive brief and submits to the AGM Operations for his recommendation to the General Manager for final approval and clearance to issue a Permit to Construct, subject to the provisions of this Order. If the facility applied for is a private commercial port, the application shall be submitted to the PPA Board for approval.

5.2.3.3 Notifies the applicant of the clearance to develop private port facility upon Board/General Manager ™s approval of the proposal.

SECTION 6. PPA Requirement on Foreshore Lease Application - The Authority ™s certification that the applied for area is in consonance with the PPA development plans shall be a pre-requisite to all foreshore lease applications with the Department of Environment and Natural Resources, whether initial or renewal. This certification may be issued at the level of the Port Manager without awaiting request from the said Department. The Port Management Offices and the Commercial Services Department shall be provided with all approved and updated port development plans.

SECTION 7. Application for Permit to Construct - Upon issuance by DENR of a foreshore lease contract/order award, the private port investor shall submit to the Authority through the Port District concerned all its construction and building plans together with its duly accomplished application for Permit to Construct. (Annex 2)*

7.1 CSD shall inform the Port District manager of the board clearance to issue a Permit to Construct.

7.2 Within three weeks from receipt of documents as enumerated in Annex 3* herein, the Port District Engineer shall evaluate the plans and documents for signature by the Port District Manager.

7.3 Upon signing of the permit to construct by the Port District Manager, his office shall issue the following:

7.3.1 Billing Notice advising proponent of the permit to construct approval, and to pay a Permit to Construct fee in accordance with the following graduated fix fees plus 10% VAT.  
Project Cost Permit to Construct Fee     Below P10 M P10,000.00     P10 M & above P10,000.00 plus .001   (1/10 of 1%) of the excess of   10 million but not to exceed   P100,000.00
7.3.2 Issue the Permit to Construct upon receipt of the Permit to Construct fee, copy furnished CSD.

SECTION 8. Certificate of Registration/Permit to Operate New and Existing Private Pier Facility/ies - Private port investors who have satisfactorily established new port infrastructures as well as port owners/operators who have developed and operated their facilities prior to the Authority ™s creation shall register with the PPA.

8.1 Certificate of Registration and Permit to Operate New Private Port - The Authority, thru the Commercial Services Department, shall issue, within three weeks, a Certificate of registration and Permit to Operate Private Port to the private port owner/operator who has submitted complete documentary requirements as stipulated in Annex 4* herein. Only private ports with official registration with PPA shall be entitled to discounted port dues as provided for under PPA Memorandum Circular 07-94.

8.2 Private Ports Handling Non-Commercial and Commercial Cargoes - All private ports that handle both non-commercial and commercial cargoes shall be considered and registered as private commercial ports.

8.3 Existing Private Ports with No Valid Operating Permits - All private ports known to be operating but not in possession of valid operating permits issued by the Authority shall be formally advised by the PMO to register with the Authority within thirty (30) days from receipt of formal notice. Failure of the private port owners to register after one month from final notice shall permanently disqualify them from availing themselves of private port privileges such as discounted port and cargo handling dues without prejudice to seeking legal remedies if called for. In this connection, the Port Manager concerned shall submit to CSD once every six (6) months a complete list of private ports duly registered and those subject for registration within his area of jurisdiction until such time that all private ports shall have been registered.

8.4 Imposition of 100% Port Charges on Unregistered Private Ports - In order to allow sufficient time for all unregistered private port operators/owners to complete documentary requirements for registration with the Authority, a moratorium on the imposition of 100% port charges on unregistered private port is hereby given in accordance with the following:

8.4.1 The Authority shall grant a moratorium on the imposition of the 100% vessel and cargo charges on existing private ports that are unregistered if such private port owners have previously enjoyed the reduced fees under the old PPA Port Tariff.

8.4.2 The moratorium shall commence from the effectivity of PPA MC 07-94 up to May 30, 1996.

8.4.3 Any amount actually paid in excess of the 50% charges under PPA MC No. 07-94 prior to the effectivity of this Order shall be applied against future billings.

SECTION 9. Cargo Handling Permit - Duly registered privately owned ports shall be allowed to undertake cargo handling operations, either on their own or by contract upon the issuance of its Certificate of Registration/Permit to Operate. They shall, submit to PPA thru the PMOs concerned the required periodic operational reports as shown in Annex 5*.

SECTION 10. Privilege Fee - For the privilege of having a permit to operate the private port, and in lieu of the percentage share from cargo handling revenues which PPA gets, the private port owners/operators shall pay the PPA through the PMO concerned, the following fees:
Private commercial ports - P20,000 per annum

Private non-commercial ports - P10,000 per annum

Marina - P5,000 per annum

Private river ports - P5,000 per annum
The privilege fee shall also extend to private port owners and operators whose cargoes are loaded/unloaded at anchorage provided such cargoes come from or are destined to their registered private port facilities.

SECTION 11. Request for Improvement - All request for improvement/expansion/rehabilitation of existing private ports during the effectivity of its approved operating permit, except for annual preventive maintenance and repair purposes, shall be evaluated by the Engineering Services Division of the PDO concerned, and approved by the District Manager. A copy of the approval shall be furnished the PDD and CSD.

SECTION 12. Transfer of Operating Permits - The sale, transfer, conveyance, assignment of operating permits shall not be entered into by the private port owner/operator without first seeking prior written clearance from the Authority.

ARTICLE III

Courses of Action on Expired Foreshore Lease/Permit

The PMO concerned shall be responsible for monitoring all private ports operating within its jurisdiction. To this end, it shall inventory all existing facilities and notify private ports with foreshore leases shall be advised to formalize their intention to renew occupancy of their respective premises, if interested. Otherwise, non application for renewal of the lease at least thirty (30) days from expiry date may be construed as an advice to effect turn-over of ownership rights to the Authority. The Port District Manager concerned is authorized to sign turn-over documents on behalf of the Authority. When a turnover is effected, the Port District Manager shall forward original copies of turnover documents to the AGM for Operations, Attention: CSD.

SECTION 13. Ports with Expired Foreshore Lease/PPA Permit to Operate -

13.1 Private port privileges on discounted port and cargo handling dues payments shall cease effective upon expiration of the ports ™ foreshore lease/PPA Certificate of Registration unless otherwise renewed.

13.2 The privilege on discounted port and cargo handling dues payment shall, however, be extended for a maximum period of 6 months provided an application for the renewal of the foreshore lease and the PPA permit to operate shall be made prior to the effectivity of the lease expiration. This extension shall be allowed to give the applicant sufficient time to complete his renewal documentation.

13.3 Owners/operators of private ports with expired foreshore leases which can no longer be renewed (those with expired second renewals) may still avail themselves of discounted port and cargo handling dues payments provided the government portion of said port facilities are covered by a lease agreement with the Philippine Ports Authority.

SECTION 14. Application to Operate Private Port with Expired Foreshore Lease - All applications to operate private ports with expired foreshore lease shall be forwarded to the Authority for appropriate action.

14.1 The Assistant General Manager for Operations, thru the Commercial Services Department shall be responsible for the overall assessment of all applications to operate private ports with expired foreshore lease permits/contracts.

14.2 If found feasible, a corresponding lease agreement for the continuous utilization and operation of the private port including all improvements introduced therein shall be prepared for management approval.

14.3 Rental payments shall be based on the prevailing market values of similar properties in the locality including other relevant economic factors.

ARTICLE IV

Miscellaneous Provisions

SECTION 15. Penalty Clause -

15.1 Violation of any of the provisions of this regulation shall subject the private port owner to the penalties enumerated under Section 43 of P.D. 857, as amended.

15.2 Private port facilities constructed without prior clearance and valid permit to construct issued by the Authority but allowed PPA registration shall be subject to payment of penalty charges which shall not be less than P20,000 in addition to the payment of the permit to construct fee.

SECTION 16. Visitorial Powers - The private port operator shall allow at any time PPA officials and authorized PPA employees entry into the private port premises to observe and inspect port operations activities and facilities in the exercise of PPA supervisory authority.

SECTION 17. Repository of Documents - A copy of all documents, communications, records pertaining to private ports shall be submitted by all departments concerned, to CSD which shall keep and maintain the same for future reference.

SECTION 18. Repealing Clause - All PPA orders, rules and regulations, policies, guidelines, memoranda or circulars inconsistent herewith are hereby repealed.

SECTION 19. Separability Clause - If any provision or section of this Order, or the application thereof to any person, corporate entity or circumstances is held invalid, the other provisions or sections of this Order, shall not be affected and shall continue to be in full force and effect.

SECTION 20. Effectivity - This Order shall take effect fifteen (15) days after its publication in a newspaper of general circulation.

Adopted: 4 Dec. 1995

(SGD.) CARLOS L. AGUSTIN
General Manager


* Text Available at Office of the National Administrative Register, U.P. Law Complex, Diliman, Quezon City

* Not Filed with ONAR