[ ERC Resolution No. 05, s. 2015, April 06, 2015 ]

A RESOLUTION ADOPTING THE AMENDED RULES TO GOVERN THE INTERRUPTIBLE LOAD PROGRAM (ILP)



Adopted: 06 April 2015
Date Filed: 07 May 2015

WHEREAS, it is a declared policy of the State to ensure the quality, reliability, security and affordability of the supply of electric power;

WHEREAS, to address the imminent power shortage and augment the limited power requirements of the distribution utilities (DUs) in Visayas and Mindanao regions, on March 10, 2010 the Commission adopted Resolution 8, Series of 2010, entitled œA Resolution Adopting the Rules to Govern the Interruptible Load Program (lLP) of Distribution Utilities (DUs)  or the ILP Rules;

WHEREAS, on May 6, 2013, the Commission adopted Resolution 8, Series of 2013, entitled œA Resolution Amending Article IV, Section 1 of the Rules to Govern the Interruptible Load Program (lLP) of Distribution Utilities (DUs) , in order to provide for a fairer and more reasonable cost recovery mechanism;

WHEREAS, the Commission in its Order dated April 11, 2014, allowed Manila Electric Company (MERALCO) to implement the ILP for its captive customers;

WHEREAS, the ILP incentivizes reduction in demand in any grid, particularly, when system reliability is jeopardized;

WHEREAS, expanding the scope of the ILP, to enable the participation of contestable customers, directly-connected customers, PEZA customers/locators and Economic Utility Enterprises is seen as making the ILP more responsive and effective in avoiding or minimizing system emergencies;

WHEREAS, on November 4, 2014, the Commission issued a Notice of Posting and Public Consultation on the proposed amendments to the œRules to Govern the Interruptible Load Program (ILP) of Distribution Utilities (DUs) , and setting the deadline to submit comments on or before November 17, 2014;

WHEREAS, on November 26, 2014, the Commission conducted a Public Consultation to discuss the comments submitted by the following stakeholders: a) Department of Energy (DOE); b) National Grid Corporation of the Philippines (NGCP); c) Philippine Electricity Market Corporation (PEMC); d) Retail Electricity Suppliers Association (RESA); e) Distribution Management Committee (DMC); f) Grid Management Committee (GMC); g) Philippine Independent Power Producers Association (PIPPA); h) MERALCO; i) Visayan Electric Company, Inc. (VECO); and j) San Fernando Electric Light and Power Company, Inc. (SFELAPCO);

WHEREAS, on December 3, 2014, the Commission conducted a Focus Group Discussion to further solicit the views of the stakeholders;

WHEREAS, on December 19, 2014, the Commission posted on its website the second (2 nd ) draft of the proposed amendments to the œRules to Govern the Interruptible Load Program (ILP) of Distribution Utilities (DUs) , and setting the deadline to submit comments on or before January 19, 2015;

NOW, THEREFORE , after considering the inputs of all stakeholders and a judicious review of all pertinent issues, be it RESOLVED, as the Commission hereby RESOLVES, to APPROVE and ADOPT the œAmended Rules to Govern the Interruptible Load Program (ILP)  hereto attached as Annex œA [*] and made an integral part of this Resolution.

This Resolution shall take effect immediately following its publication in a newspaper of general circulation in the Philippines and shall continue to be in force until recalled or vacated by the ERC.

Let copies of this Resolution be furnished the University of the Philippines Law Center-Office of the National Administrative Register (UPLC-ONAR), the NGCP, all distribution utilities, RESA and PIPPA.

Pasig City, April 6, 2015.

(SGD) ZENAIDA G. CRUZ-DUCUT
Chairperson


(SGD) ALFREDO J. NON
Commissioner
(SGD) GLORIA VICTORIA C. YAP-TARUC
Commissioner


(SGD) JOSEFINA PATRICIA A. MAGPALE-ASIRIT
Commissioner



[*] Text Available at the Office of the National Administrative Register, U.P. Law Complex, Diliman, Quezon City.